Before setting a 2027 sales target, test whether one real week of delivery can support the work. Count available labor hours, subtract known non-job time and a separate allowance for uncertainty, then compare the remainder with work already committed. A negative balance is a decision to resolve before making another promise.
This is a planning exercise for founders and operators of service businesses, not a forecast of industry demand. Use it during 2027 budget preparation, then update it with your own weekly records. The figures below are hypothetical; they are not results from any business associated with Jay Zaabri.
Start with one crew group and one week
Choose a specific week, location and type of work. Keep separate worksheets for skills or equipment that cannot substitute for one another. Available hours in one market do not necessarily cover a shortage in another.
Use person-hours throughout: two people working eight hours each equal 16 person-hours. If your job estimates use crew-days, convert them using the actual crew size and hours per day. Do not mix labor hours with elapsed calendar time.
Build a delivery budget in six lines
A. Scheduled paid labor hours: add the hours scheduled for the people in this group before deductions. Include only staffing actually expected to be available; record an unfilled role as a separate scenario.
B. Known non-job hours: subtract paid leave, training, travel and other time that your job estimates do not already include. Apply one convention consistently. If travel is already counted in job estimates, leave that same travel out of B.
C. Protected allowance: set aside hours for uncertainty not already counted in B or the job estimates. Choose this using your own records and explain the assumption. There is no universal percentage in this worksheet. A known callback belongs in the workload estimate, not in an unnamed contingency a second time.
D. Planned delivery budget = A − B − C. Keep a negative result visible; do not replace it with zero.
E. Committed work: total the remaining estimated person-hours due in that week, including known return visits. Include work that is committed but not ready, and flag its missing prerequisite separately. Removing it from the workload would hide the commitment.
F. Capacity balance = D − E. A negative result identifies a shortfall against these assumptions. A positive result is only an hours check: materials, access, sequencing, equipment, skills and the actual calendar still need to work.
Worked example: a 16-hour gap
Suppose eight field employees are each scheduled for 40 paid hours. A is 320. The planner identifies 64 hours of known non-job time and protects another 32 hours for uncertainty. D is therefore 224 person-hours.
The remaining work due that week totals 240 person-hours. F is 224 − 240 = −16. The plan already has a 16-hour gap before accepting anything else. These are illustrative assumptions, not recommended staffing ratios.
Now test two independent scenarios. If one employee’s 40 scheduled hours become unavailable while the other assumptions stay fixed, the gap becomes 56 hours. If staffing stays unchanged but a new job requires 24 hours in that week, the gap becomes 40 hours. Do not combine the scenarios unless both conditions apply.
Turn the gap into a decision
First check the inputs: are remaining job hours current, is non-job time counted once, and are customer commitments accurately recorded? Then identify the constraint and a named decision owner. Options may include agreeing a different delivery date, changing the work sequence, or adding confirmed qualified capacity. Record the effect in hours and the conditions before treating an option as a solution.
Moving work to another week also moves its capacity requirement. Recheck the receiving week and agree changes with the people affected. Do not treat overtime, a prospective hire or unconfirmed subcontractor availability as capacity already secured.
For each decision, record the owner, action, deadline, remaining condition and who will communicate with the customer. Use the operating handoff checklist to keep a requested date distinct from a confirmed commitment.
Use weekly evidence in the 2027 plan
Repeat the exercise for the opening weeks of 2027 and for known seasonal peaks, holidays or staffing changes. An annual average can conceal an overloaded week. Keep the assumptions for booked work separate from a scenario for potential sales, and keep job mix visible: the same revenue target can require different amounts of labor.
At the end of each week, compare estimated remaining job hours with the actual work performed and work carried forward. Record why the difference occurred. Adjust the next estimate or allowance using those observations, rather than quietly rewriting the original plan.
This worksheet does not test cash flow, profitability or legal requirements. Those need their own review. Its purpose is narrower: make the workload assumption and the next operating decision explicit.
Download the two-page worksheet
Download the 2027 Capacity Planning Worksheet (PDF, two pages). Page one is a reusable planning sheet; page two shows the worked example and independent stress scenarios. The definitions and example are also available in the text above.
Prefer automatic calculations? Download the Weekly Capacity Calculator (XLSX). Replace the clearly labeled hypothetical inputs with your own person-hours to calculate the delivery budget, capacity balance and two independent stress scenarios. Includes missing-input checks and a decision record. The formulas and definitions are explained above; no signup is required.
A question for your next planning meeting: Which assumption would break first if one person were unavailable next week?