Appogee, an industrial campus in Watkins, Colorado, was the largest restoration job I handled in my career. We won the full job, and our team completed the entire restoration in under 60 days. I helped coordinate the review of the estimate as our team worked through the buildings and trades.

One building helps explain why that review mattered. It had two different roof assemblies in the estimate. One section called for TPO, a thermoplastic membrane over metal. Another called for EPDM, a rubber membrane. A spreadsheet row labeled “roof” would have hidden a distinction that mattered to anyone measuring, pricing or ordering that work.

One campus, several ways to count
The Colorado Real Estate Journal reported that the property included 16 buildings when it changed hands in 2018. That was a count of the buildings in the real estate transaction. The restoration team had a different job: identify the work proposed for each building and trace it back to a measurement, a photograph or a trade estimate. Read the newspaper’s property history.
You can see the difference in a public record for Building 11. On August 20, 2025, Arapahoe County issued a commercial reroof permit with a listed valuation of $436,363. That figure belongs to one permit. The August 2024 replacement-cost estimate priced a much broader proposed scope. See permit BLD-2025-02177 on page 9 of the county report.

How I’d check the next multi-building estimate
I’d start with one roof section. If the cost goes up between two versions, did the measured area change, did the unit price change, or did a new task enter the scope? Removing and reinstalling rooftop equipment, for instance, is a different explanation from needing more roofing material. The total alone can’t tell you which question to ask.
For every item under review, I’d put the building and roof section, the proposed work, the quantity and unit, the supporting photo or measurement, and the estimate version on the same row. Then give that row to someone who hasn’t walked the campus. Can they point to the roof section and explain what changed? That’s the test I’d use before signing off on the review.
For the next step, I use a similar approach to make sure the team taking over knows what it owns. Read my operating handoff checklist.