When Ken Lodi and I looked at a commercial roof in West Hollywood, the solar equipment was already up there. I wrote about the question the owner had about monthly costs. There’s another question I’d want answered before comparing two roof bids: when the equipment has to move, whose price includes putting it back into service?
The answer should be in the written scopes. I’d ask the building manager to identify the equipment, its owner and the company that services it. Photovoltaic modules generate electricity. Solar thermal collectors supply heat. I’d have the service provider identify the system from its records before asking anyone to price the work.
Give both bidders the same four questions
| Stage | Ask the bidder | What the owner should receive |
|---|---|---|
| Before the roof bid | Who owns the equipment and who can authorize taking it out of service? | Equipment record, owner approval and contact for the service provider. |
| Removal and storage | Who prices removal, records condition and takes custody while the roof is open? | Itemized scope, inventory, storage location and responsible contact. |
| Roof ready for reinstallation | Who confirms that roofing work and any required inspection are complete in that area? | Dated release from the person named in the roofing scope. |
| Return to service | Who reinstalls the system, checks operation and hands it back to the owner? | Service report with test results, date and a contact for unresolved items. |
For each row, write down a company, a named contact and where the cost appears. If an owner plans to hire the solar contractor directly, show that cost alongside the roofing bid. A blank is a question to resolve before award.
The two bids that look comparable
Suppose one bidder includes removing and storing the equipment. The other includes those items plus reinstallation and a return-to-service test. Both can accurately describe their price as including “solar removal.” I’d ask the first bidder for the two missing prices and check who pays for extra storage if the roof inspection slips a week. Then I can compare the same finished job.
For photovoltaic equipment, the National Renewable Energy Laboratory’s operations and maintenance guide identifies a specific document worth asking about: an overburden waiver. Where one applies, it can set out responsibilities for moving equipment so the roofer can get access. Ask the roofing warranty issuer and the system owner what their documents require on this building.
My last question goes to the person who runs the building: when the roofer tells you the roof is finished, whose report will tell you the solar equipment is working again? I’d want that name before signing the bid.